S.No |
Clients |
Description |
1. |
Water
& Power Development Authority |
Installation, Testing & Commissioning of Re-heater Tube Elements of Boiler for 250 MW
Init No. 1, TPS, Jamshoro.
Erection, installation, testing and commissioning of make-up water system & laying of
lines upto 1200 mm dia for cooling towers and chemical treatment plant, for unit No. 01
& 02 (2 x 110 MW) at Thermal Power Station, Guddu.
Client: M/s SKODA, Czeck.
Laying of M. S. Pipe 30" dia, 6,000 M from Power Station to River Indus and installation
of pumping system for (880MW) Oil fired Thermal Power Station, Jamshoro.
Supply, Erection & lying of make-up water piping system of (880 MW) Oil fired Thermal
Power Station, Jamshoro, Pakistan.Supply, installation and laying of low pressure pipe
line of 18" Ø for water disposal system for unit No.: 1, 2, 3 & 4 (880 MW) Oil Fired
Thermal Power Station, Jamshoro, Client: RE, TPS Jamashoro / WAPDA
Supply, installation, testing and commissioning of fire protection system, 450 MW
(General Electric) Combined cycle project. This includes the supply, installation of
Fire equipments, Pumping system, lying of Pipelines of various sizes, etc. Guddu,
Kashmore, Pakistan.
Client:PD, WAPDA Consultant: Gibbs and Hills Inc, USA Supply, laying of water,
sewerage and gas pipeline of various sizes for residential units 1020 Nos. of different
categories at Thermal Power Station, Guddu, Pakistan. Client: PD, Guddu / WAPDA
Construction and arrangements for disposal sewerage system and providing,
installation of pumping system at Thermal Power Station, Guddu. Client: SE(C), Guddu
/ WAPDA
Supply, installation & laying of pipelines erection, testing and commissioning of 02 Nos.
HSD Oil Tanks for 450 MW combined cycle project, Guddu, Pakistan. Laying of fire
fitting pipeline 8"-12"ø for 880 MW, Thermal Power Station, Jamshoro, Pakistan.
Supply laying of gas pipeline for main power station 12” dia for Thermal Power Station,
Guddu, Kashomore, Pakistan
Providing & laying of High pressure steam pipeline for unit No.1, 2, 3 & 4 (880 MW)
Oil fired Thermal Power Station, Jamshoro, Pakistan. HP pipeline for gas & oil for boiler
12.50MW x 4 units at Thermal Power Station, Sukkur Providing, installation and lying
of Sui Gas pipe line for Housing project at Thermal Power Station, Guddu. Supply,
installation fuel oil decanting system for Thermal Power Station, Guddu, Kashmore,
Pakistan Installation and modification of gas station with piping for 880MW oil fired
Thermal Power Station, Jamshoro, Pakistan Laying of pipeline on EPC basis for 310
MW makeup water Chinese Unit at Thermal Power Station, Muzaffargarh.
|
2. |
Pakistan
State Oil Company Limited (PSO)
|
Laying and commissioning of 42” dia. Pipeline & installation of pumps at Zulifiqarbad
Terminal, Port Qasim, Karachi.
Laying / commissioning of 24”dia Pipeline between main railway line and Gandhara
Nissan Factory connecting FOTCO Jetty with Zulfiqarabad Oil Terminal, Pakistan.
Construction of Horizontal Tank and Pipeline system at Juglot Depot.
Erection / commissioning of Pipeline of 16” dia. for supply of furnace oil to AES Power
Complex.
Erection / commissioning of MS & SS Pipelines at ( OP-V ) Terminal for fuel and
chemical at Karachi Port Trust, Keamari, Pakistan.
Supply, installation, laying and commissioning of S.S. and C.S. piping at jet fuel farm
facilities at new Lahore International Airport.
Erection / commissioning of Process Piping, Installation / testing of Pumps for PSO
Revamp Project for Lube Oil Facilities at Korangi, near NRL Refinery, Karachi. |
3. |
Asia
Petroleum Limited, Karachi. |
Hub River Fuel Oil Pipe Line Project for 40” dia. at PSO Zulfiqarabad Oil Terminal Pipri. |
|
|
|